The Sacramento Drill Tower, Sacramento, California, is an unusual building. A large water tank takes up two-thirds of the 9,476-square-foot, concrete facility. The other third is occupied by offices for the city’s firemen, administrators and IT personnel. For years, these occupants were cooled and heated by a four-pipe chilled-water and boiler system. When that system failed, the city installed our Variable Refrigerant Flow (VRF) technology. The result: immense energy savings and easy maintenance.

When the building’s old chilled-water compressor failed, Nghiem Nguyen, the mechanical maintenance supervisor for City of Sacramento Facility Maintenance turned to our systems. “I was fully impressed by VRF and Mitsubishi [Electric]. They were so far ahead of everybody else when it came to VRF. The engineering aspect and operational maintenance were really in place . . . I knew this would be a great application. It wouldn’t be hard to retrofit since we wouldn’t have to open up the walls to pull out old lines. The real selling feature, though, was the energy savings. I knew it was going to be huge for us.”

Ngyuen was correct. Comparing pre- and post-installation energy data shows that the system’s efficiency has led to a total energy savings (kBtu usage) of 50 percent, and a total cost savings of 19 percent. Money has also been saved on maintenance: “We’re saving so much money on service calls and maintenance calls. We probably have a tenth of the service calls we had before.”

The Sacramento Drill Tower project was so successful that it inspired the city to use VRF at two more facilities. To learn more, check out the case study.

No comments:

Post a Comment